CORE Builder Group
§ Journal · SIRS & Compliance

Q4 SIRS countdown: what condo boards need to have done before October 1

The December 31 SIRS deadline is 180 days away. For boards with Phase 2 milestone findings and no contractor under contract, October 1 is the real deadline — here is the math and what needs to happen before then.

July 4, 2026Ryan Perez6 min read

The Structural Integrity Reserve Study deadline under Florida Statute § 553.899 is December 31, 2026. As of early July, there are roughly 180 days until that date. For condo associations that have not yet completed their SIRS or begun the structural repairs required by Phase 2 milestone inspection findings, that number is not as large as it sounds. A structural repair project in an occupied South Florida residential building typically takes 8 to 16 weeks from permit issuance to final inspection closeout — and the permit application itself, with engineer-stamped drawings, takes 3 to 6 weeks to prepare and submit after a contractor is engaged. That math puts the real decision deadline for associations that want to be in compliance by December 31 closer to October 1 than to December 31.

What needs to be done before December 31

Florida's SIRS requirement has two components. First, the study itself: a licensed structural engineer or reserve specialist must produce a written report covering the structural components and life safety systems of the building, their estimated remaining useful life, and the reserve funding amount needed to cover projected repair costs. Second, for associations whose milestone inspection produced Phase 2 findings — meaning the engineer observed substantial structural deterioration requiring further investigation and repair — the repairs must be completed, inspected, and permitted closed. The SIRS is a documentation obligation. Phase 2 repair completion is an active construction obligation. Both carry December 31 deadlines, but boards that have completed their SIRS and believe they are finished while Phase 2 findings remain open are not in compliance.

Why October 1 is the real contractor engagement deadline

If a condo board has received Phase 2 milestone inspection findings and has not yet engaged a structural repair contractor, October 1 is the realistic last date to begin that engagement and maintain any reasonable confidence in reaching December 31 in compliance. The math: the pre-construction phase after a contractor is engaged — scope finalization with the engineer, contract execution, permit application preparation with engineer-stamped drawings — takes a minimum of 3 to 4 weeks. Miami-Dade County building permit review for structural repair projects typically takes 3 to 6 weeks on an expedited track. That places permit issuance in late October at best when contractor engagement begins in early October. An 8-week repair project runs through late December. A 12-week project runs past the deadline without an approved extension. Boards that are not already under contract with a structural repair contractor have a window that is narrowing every week.

If your SIRS is not yet commissioned

The SIRS is a report, not a construction project, and it can be completed faster than a repair scope — but not instantaneously. A licensed structural engineer producing a SIRS for a mid-size condominium typically needs 4 to 8 weeks from the initial site walk to the final written report. If your association has not yet commissioned a SIRS, the study can still be completed before December 31 with urgency — but engaging the engineer now rather than in September or October is the difference between adequate time and a sprint with no margin. If your building also has milestone inspection findings, the SIRS and the repair scope should be coordinated with the same or closely communicating engineers so the reserve calculation reflects the actual repair cost of the current structural condition.

The reserve funding question boards most often defer

The SIRS requirement does not only require that the study be completed — it requires that the association's reserve funding be adequate to cover the amounts the study identifies as necessary. Associations that complete the SIRS and find their reserves significantly underfunded face a second obligation: whether to raise assessments to meet the reserve target, take a loan to fund the deficiency, or present a documented funding plan that acknowledges the shortfall. Florida statute requires that the study reflect the actual condition and actual reserve need — not a version of the numbers that looks more manageable. Boards that are navigating this position need legal counsel and a financial advisor alongside the structural engineer, and that process takes time to conduct correctly. Beginning it now rather than in the fall is not an option — it is the minimum required.